Client
Parking Building BV
Location
Heverlee
Architect
SVR Architects
Engineering consultancies
Witteveen+Bos and Istema
Construction period
10/2024 - 2026
Project size
27,000 m²
MobHub
STRABAG Belgium was awarded the contract for the turnkey construction of a new multi-storey parking facility at Arenberg Park in Heverlee.
The client, Parkeergebouw BV—a consortium of surrounding buildings supported by KU Leuven—commissioned STRABAG Belgium for the turnkey construction of a new nine-storey parking facility.
STRABAG is responsible for earthworks, structural works, finishing, technical installations, and environmental construction. Each floor spans 3,000 m², bringing the total building area to 27,000 m² and providing space for 850 vehicles.
Construction began in autumn 2024 and is scheduled for completion in spring 2026.